Construction sign with text Road Work with road in the background

Construction projects


Construction Notifications

Do you want notifications or updates on construction projects? You can register by clicking the button below. Make sure to select the "Construction" topic. If you've already registered, you can update your preferences by signing in. Please enter your home address and the City will send notifications to the areas affected by each project.




Main Street Widening and Reconstruction

Spring 2023 - Spring 2024

Project overview

Widening and major improvements to existing Main Street/Herriman Highway between 6225 West and 7300 West. Addition or replacement of culinary and secondary water lines, curb and gutter, sidewalk, drainage improvement, landscaping and park strips, pavement, and re-striping to add a middle turn lane, bike lanes, and a shoulder.

Project webpage

Latest update

(Updated Nov 14) 

  • 7300 West to Split Oak Drive:
    • Asphalt paving is complete. Roadway striping will be completed Nov 18-20, weather permitting.
      • Cool-weather measures were in place to assure proper pavement application and curing during the fall season. Paving will not take place during the winter.
    • Sidewalk installation: sidewalks are being prepared and concrete is being poured through the end of November, weather permitting.
      • Oak Leaf Elementary safe walk route sidewalk: Due to unforeseen overall project delays, the sidewalk used in a permanent Safe Walk Route for Oak Leaf Elementary School students living in the area of 7300 West and south of Main Street was not completed by the beginning of the school year. Jordan School District buses are serving as temporary shuttles until the winter school holiday. Constructing the sidewalk from 7300 West to Dansie Oaks Blvd. remains a top priority. Preparation for the sidewalk, including grading and utility relocation, is ongoing. Anticipated completion for the sidewalk is early winter.
      • A school crosswalk with speed-reducing flashing lights will be installed at the intersection of Main Street and Dansie Oaks Blvd. A crossing guard will be placed at this location starting in January. A full traffic signal is planned for this location in coming years but will not be a part of this project.
  • 6225 W to 6400 West roadway section has been paved and completed.
  • 6400 West intersection has ongoing utility work. It will not have permanent pavement right now, but will receive temporary pavement for the winter, which is expected by the end of November.
  • Paving work will stop during the winter but will resume in the spring. Other work will progress during the winter—some landscaping work, street lights, sidewalks (with cold-weather measures), and street signs.

Impacts/expectations

  • Noise and dust
  • Heavy equipment
  • Occasional lane restrictions
  • Minimal full closures
  • Work hours: 7:00 a.m. - 9:00 p.m.
  • 10-foot minimum access to be maintained for homes and businesses
  • Any property disturbance will be relocated or replaced with "like kind"

Contractor


Project budget

$10,000,000




Juniper Crest Rd/Patriot Ridge Dr Traffic Signal

June 2023 - September 2023 (Complete)

Project overview

Installation of four-way traffic signal at the intersection of Juniper Crest Road and Patriot Ridge Drive/Mount Ogden Peak Road.

Latest update

(Updated Sept 18) 

  • The traffic signal has been installed and is functioning.
  • Sidewalk ramps on corners of the intersection failed their 28-day maximum weight-bearing test and may need to be replaced.
  • Unforeseen materials delays caused the project to be delayed until September instead of completion by the beginning of the school year.

Impacts/expectations

  • Noise and dust
  • Heavy equipment
  • Sidewalk closures during reconstruction and installation
  • Occasional lane restrictions
  • Minimal full closures only when signal poles are installed
  • Work hours: 7:00 a.m. - 9:00 p.m.

Contractor


Project budget

$320,000




Asphalt Resurfacing

August - September 2023 (Complete)

Project overview

Each year, the City resurfaces roadways with preservation treatment as standard maintenance to preserve the life of the road. The list of roads is based on a multi-year rotating schedule. Locations are spread throughout the city, including neighborhood roads, cul-de-sacs, and some more major roads.

Latest update

The project is now complete. Thank you for your patience and cooperation with this project that impacts many residents directly.

(Updated Oct 1)

Impacts/expectations

  • Road closures during work
  • Noise, heavy equipment
  • Work hours: 7:00 a.m. - 7:00 p.m.

Contractor



Project budget

$1,600,000




13200 South (Herriman Rose Blvd) Connection

Fall 2023 - Spring 2024

Project overview

Road and utility installation to connect Herriman Rose Boulevard/13200 South to Mountain View Corridor. This is a development company-led project in consultation with the City.

Latest update 

(Updated Sept 12)

  • Construction will begin in Fall 2023 with installation of utilities, water, and stormwater infrastructure, as well as pre-grading work for the road itself. Due to wintertime temperatures, curbing and pavement will not be completed until the spring of 2024, after which the roadway will open to the public.

Impacts/expectations

  • Noise
  • Dust
  • Heavy equipment
  • Road is not anticipated to be open until the spring in 2024

Contractor

  • TBA


Project budget

Reimbursement project




7300 West Widening and Improvement

Winter 2023 - Fall 2024

Project overview

Widening and improvement of approximately 1,500 feet of 7300 West, between McCuiston Avenue/Arla J Way and Hall Crossing Drive. Improvements include new asphalt, curb, gutter, sidewalk, street lighting, and infrastructure for storm drain and water.

Latest update 

(Updated Aug 22)

  • Construction is expected to start in late winter/early spring 2024 and be complete in the fall.
  • Property acquisition is in progress; project expected to go to contractor bid in late fall/early winter

Impacts/expectations

  • No impacts expected until late winter 2023/2024

Contractor

  • TBD; bid expected in late fall/early winter 2024


Project budget

$2,950,000




13400 South/Bangerter Interchange (UDOT)

Fall 2023 - Fall 2025

Project overview

This project occurs outside of Herriman but greatly affects our residents. From the fall of 2023 - fall 2025, the Utah Department of Transportation (UDOT) will be overseeing the transformation of stoplight intersection on Bangerter Highway at 9800 South, 13400 South, and 2700 West to freeway-style interchanges. When the intersection is transformed, Bangerter Highway will eventually pass under 13400 South.

The project will include a closure of east/west traffic on 13400 South across Bangerter Highway from fall 2024 to late summer 2025.

Full project details can be found on UDOT's website.

Latest update 

(Updated November 14th)

Closure Alert

  • Overnight closure on Friday, November 17, from 11 p.m. to 7 a.m. between 13400 South and 2700 West as they permanently remove the pedestrian bridge at 13400 South.
  • Access to the pedestrian bridge as been terminated. Pedestrians can still cross Bangerter Highway at 12600 South and 3600 West.
  • Traffic in both directions on Bangerter Highway will be detoured via 13400 South and 2700 West.
  • Drivers can expect short-term lane closures on 13400 South for east and west traffic.

Closure Alert

  • Overnight closure on Saturday, November 18, from 11 p.m. to 7 a.m. between 2700 West and Redwood Road as they permanently remove the pedestrian bridge at 2700 West.
  • Access to the pedestrian bridge will close on Wednesday, November 15. Pedestrians can still cross Bangerter Highway at 3600 West and Redwood Road.
  • Traffic in both directions on Bangerter Highway will be detoured via 12600 South and Redwood Road.
  • Drivers should expect lane closures on Bangerter Highway between 2700 West and 12600 South.

(Updated October 23rd)

  • Lane shifts due to roadway utility work will begin as early as Saturday, November 4th with median removal starting Wednesday, October 25.
  • 13400 South and 2700 West pedestrian bridges over Bangerter Highway will be removed on November 17 and 18, respectively. Preparation work with traffic impacts will begin on November 15.
  • Work will start in fall 2023, but major, ongoing traffic impacts will begin in spring 2024.

Impacts/expectations

  • Travel impacts begin in spring 2024
    • Occasional lane closures
    • Travel delays
    • Traffic pattern shifts
  • Noise, dust, vibration





Hamilton Farms Stormwater Improvement

March - September October 2023 (Complete)

Project overview

New installation or replacement of storm drain pipe and infrastructure in the Hamilton Farms neighborhood. This will help more efficiently direct stormwater during heavy rain or snow events and ensure balanced use of detention ponds.

Latest update 

(Updated October 12)

  • The primary project has been completed and the stormwater infrastructure is functioning property
  • Some road damage was revealed during the project along McCuiston Avenue. The road damage has been repaired and is complete.

Impacts/expectations

  • Main project impacts are complete
  • Upcoming road repair impacts:
    • Noise
    • Dust
    • Heavy equipment
    • Occasional lane restrictions
    • Occasional full road closures (with notice)

Contractor

  • J & B Excavating


Project budget

$1,700,000