Construction Projects
Stay up to date on major projects happening within Herriman.
Click the project link below to jump to that part of the page.
Main Street Widening and Reconstruction
December 2023 - Spring 2024
Project overview
Widening and major improvements to existing Main Street/Herriman Highway between 6225 West and 7300 West. Addition or replacement of culinary and secondary water lines, curb and gutter, sidewalk, drainage improvement, landscaping and park strips, pavement, and re-striping to add a middle turn lane, bike lanes, and a shoulder.
Latest update
(Updated Sept 25)
- In order to finalize roadway grading and pavement of Herriman Main Street, the stretch from 6225 W to 6400 W will be CLOSED from Tuesday, September 26th, through Friday, September 29th. Watch for detour signage in the area that will lead you around the construction. Those living in the area will still be allowed access to their property during the work.
- Due to project delays, the sidewalk used in a permanent Safe Walk Route for Oak Leaf Elementary School students living in the area of 7300 West and south of Main Street was not completed by the beginning of the school year. Jordan School District buses are serving as temporary shuttles until the winter school holiday. Constructing the sidewalk from 7300 West to Dansie Oaks Blvd. remains a top priority. Preparation for the sidewalk, including grading and utility relocation, is ongoing. Anticipated completion for the sidewalk is early winter.
Impacts/expectations
- Noise and dust
- Heavy equipment
- Occasional lane restrictions
- Minimal full closures
- Work hours: 7:00 a.m. - 9:00 p.m.
- 10-foot minimum access to be maintained for homes and businesses
- Any property disturbance will be relocated or replaced with "like kind"
Contractor
- Landmark Excavating
- Superintendent: Tom Hibdon
- 385-237-6702
- tomh@landmarkexc.com
Project budget
$10,000,000
Juniper Crest Rd/Patriot Ridge Dr Traffic Signal
June 2023 - September 2023
Project overview
Installation of four-way traffic signal at the intersection of Juniper Crest Road and Patriot Ridge Drive/Mount Ogden Peak Road.
Latest update
(Updated Sept 18)
- The traffic signal has been installed and is functioning.
- Sidewalk ramps on corners of the intersection failed their 28-day maximum weight-bearing test and will be replaced.
- Unforeseen materials delays caused the project to be delayed until September instead of completion by the beginning of the school year.
Impacts/expectations
- Noise and dust
- Heavy equipment
- Sidewalk closures during reconstruction and installation
- Occasional lane restrictions
- Minimal full closures only when signal poles are installed
- Work hours: 7:00 a.m. - 9:00 p.m.
Asphalt Resurfacing
August - September 2023
Project overview
Each year, the City resurfaces roadways with preservation treatment as standard maintenance to preserve the life of the road. The list of roads is based on a multi-year rotating schedule. Locations are spread throughout the city, including neighborhood roads, cul-de-sacs, and some more major roads.
(Updated Sept 22)
Impacts/expectations
- Road closures during work.
- Residents must remove all vehicles from the affected street before, during, and after the treatment process until crews have removed the closure barriers. The contractor will provide notice via a door hanger note to residents several days in advance.
- Noise, heavy equipment
- Work hours: 7:00 a.m. - 7:00 p.m.
Contractor
- Intermountain Slurry Seal
- Supervisor: Luis Munoz
- 385-214-6182
- Morgan Pavement (complete)
- Specialty Applicators (complete)
Project budget
$1,600,000
13200 South (Herriman Rose Blvd) Connection
Fall 2023 - Spring 2024
Project overview
Road and utility installation to connect Herriman Rose Boulevard/13200 South to Mountain View Corridor. This is a development company-led project in consultation with the City.
Latest update
(Updated Sept 12)
- Construction will begin in Fall 2023 with installation of utilities, water, and stormwater infrastructure, as well as pre-grading work for the road itself. Due to wintertime temperatures, curbing and pavement will not be completed until the spring of 2024, after which the roadway will open to the public.
Impacts/expectations
- Noise
- Dust
- Heavy equipment
- Road is not anticipated to be open until the spring in 2024
Contractor
- TBA
Project budget
Reimbursement project
7300 West Widening and Improvement
Winter 2023 - Fall 2024
Project overview
Widening and improvement of approximately 1,500 feet of 7300 West, between McCuiston Avenue/Arla J Way and Hall Crossing Drive. Improvements include new asphalt, curb, gutter, sidewalk, street lighting, and infrastructure for storm drain and water.
Latest update
(Updated Aug 22)
- Construction is expected to start in late winter/early spring 2024 and be complete in the fall.
- Property acquisition is in progress; project expected to go to contractor bid in late fall/early winter
Impacts/expectations
- No impacts expected until late winter 2023/2024
Contractor
- TBD; bid expected in late fall/early winter 2024
Project budget
$2,950,000
13400 South/Bangerter Interchange (UDOT)
Fall 2023 - Fall 2025
Project overview
This project occurs outside of Herriman but greatly affects our residents. From the fall of 2023 - fall 2025, the Utah Department of Transportation (UDOT) will be overseeing the transformation of stoplight intersection on Bangerter Highway at 9800 South, 13400 South, and 2700 West to freeway-style interchanges. When the intersection is transformed, Bangerter Highway will eventually pass under 13400 South.
The project will include a closure of east/west traffic on 13400 South across Bangerter Highway from fall 2024 to late summer 2025.
Full project details can be found on UDOT's website.
Latest update
(Updated Sept 7)
- Work will start in fall 2023, but traffic impacts will begin in spring 2024.
Impacts/expectations
- Travel impacts begin in spring 2024
- Occasional lane closures
- Travel delays
- Traffic pattern shifts
- Noise, dust, vibration
Contact information
- Hotline: 888-766-ROAD (7623)
- Email: bangerter@utah.gov
- Website: udot.utah.gov/bangerter
Hamilton Farms Stormwater Improvement
March - September 2023
Project overview
New installation or replacement of storm drain pipe and infrastructure in the Hamilton Farms neighborhood. This will help more efficiently direct stormwater during heavy rain or snow events and ensure balanced use of detention ponds.
Latest update
(Updated August 29)
- The primary project has been completed and the stormwater infrastructure is functioning property
- Some road damage occurred during the project. Additional work will be done to repair the road. A timeline will be published when it becomes available.
Impacts/expectations
- Main project impacts are complete
- Upcoming road repair impacts:
- Noise
- Dust
- Heavy equipment
- Occasional lane restrictions
- Occasional full road closures (with notice)
Contractor
- J & B Excavating
Project budget
$1,700,000