![]()
|
City Road Projects
11800 South Road Changes Residents of Herriman that drive along 11800 South at about 5600 West have noticed the new road (Daybreak Blvd.) that has been constructed by Daybreak in South Jordan. Daybreak Blvd. is planned to connect 11800 South directly to 11400 South. This will give residents direct access to the 11400 South intersection at the Bangerter Highway and in the future 11400 South will connect directly to I-15. This connection is also planned to reduce the volume of traffic on 11800 South between 4000 West and 5600 West. 11800 South will no longer be a truck route in this area. The design approved by South Jordan for this intersection includes removing a portion of 11800 South. The proposed design will require West bound traffic on 11800 South to come to a T-intersection with Daybreak Blvd. The connection is planned to be completed by the first of December 2008. While the connection of Daybreak Blvd. of 11800 South is part of the long range transportation plan, the T-intersection is temporary until the Mountain View Freeway is constructed. The City of Herriman is currently reviewing the effects of this design and will be working with South Jordan City with recommendation to alleviate the negative effects of this change. Contact Gordon Haight, City Engineer by email or call 801-446-5323 with questions, comments or recommendations. Towne Center Main Street Detour The City of Herriman has been working with the Jordan School District, Salt Lake County and the Towne Center Developers to develop an amenity filled City Center that will include an elementary school, County Library and a state of the art County Recreation Center. As this area develops it will include other civic and government buildings including a new city hall, as well as office, commercial, retail and residential developments. This project includes the construction of a new Main Street and the abandonment of the existing Main Street. The new Main Street is currently under construction and is projected to be opened in the Summer of 2009. The elementary school, library and recreation center are all planned and design to use portions of the existing Main Street for their projects. In order to meet construction schedules to meet planned opening deadlines the City has agreed to the closure of a portion of Main Street on February 1st. The developers have agreed to construct a temporary by-pass road until the new Main Street is completed. All traffic traveling on Main Street after February 1st will be required to drive on the temporary bypass road. The City is currently reviewing the detour design and is making sure every effort to make this detour as effective as possible is used. If you have any questions or comments please email Gordon Haight or call at 801-446-5323.
Electric Utility Work
Herriman City Main Street Reconstruction
Herriman Parkway - 4570 W to 5050 W
Mountain View Corridor Project
Rose Cayon Road Overlay
City Water Projects
Development Projects
Miscellaneous Projects
|
