construction

Academy Parkway Construction

A portion of Academy Parkway will be closed for road work on Tuesday, September 18th.

Chip Seal 2018 Herriman Chip Seal map

Beginning the week of September 17, 2018, Herriman City has contracted with Consolidated Paving & Concrete to place an asphalt chip seal on streets throughout the city.

The work will normally be completed between the hours of 7:00 am to 7:00 pm. The chip seal consists of rubberized liquid asphalt applied to the existing surface, which is then covered with aggregate rock called “chip”. The chip seal takes about one to two hours to cure completely. The streets will receive a fog seal approximately one week after the chip seal is applied, this will give the road a black finish. There will be traffic control and flagmen to ensure the safe passage while the work is being completed.

The map above shows the roads in blue that will be receiving the chip seal treatment. Expect some delays and choose alternate routes, if possible.

The chip seal schedule is as follows:

  • September 17 – Spring Canyon Road
  • September 18 – Rose Crest Road / Juniper Crest Road
  • September 19 – 13400 South / 12900 South / Herriman Blvd
  • September 20 – Anthem Park Blvd / Freedom Park Blvd

The fog seal schedule is as follows:

  • September 24 – Spring Canyon Road / Rose Crest Road / Juniper Crest Road
  • September 25 – 13400 South / 12900 South / Herriman Blvd / Anthem Park Blvd / Freedom Park Blvd

Schedules are subject to change due to weather conditions and material availability.

Redwood Road (SR-68) & Porter Rockwell Blvd Intersection Reconstruction Redwood/Porter Rockwell

UPDATE:
Work at the intersection with SR-68 began August 27th, this work is expected to last approximately two months. Work includes improvements to the intersection of Redwood Road and Porter Rockwell Boulevard which will include widening to accommodate additional turning movements, storm drainage, sidewalks, pedestrian ramps, signals, and lighting. The left turn movement from eastbound Porter Rockwell onto northbound Redwood Road will be closed for the next two months. Please follow any posted detour signs.

Cyclists
Please Note: During construction there will not be any bike lanes or shoulders available for use. If possible find an alternate route.

TRAFFIC:

Redwood Road Traffic
Most of the time on Redwood Road at the intersection there will be two southbound lanes. For northbound travel on Redwood Road there will be one continuous northbound lane and one left turn lane onto Porter Rockwell.

Porter Rockwell Boulevard Traffic
For eastbound travel on Porter Rockwell Boulevard, the left turn movement onto northbound Redwood Road will be closed, however a right hand turn movement onto southbound Redwood Road will be maintained.

An alternate route is provided at 13400 South and Mountain View Corridor as well as a detour route. Please follow the detour using 13400 South for access to northbound Redwood Road.

Please slow down and watch for construction crews and equipment. Be prepared for reduced lanes, heavy equipment, sudden stops, and delays.

Stay Informed
Please share this information with anyone who may benefit from it. You can receive weekly updated information about expected impacts during construction. Just send an email and request “Porter Rockwell Updates” to: shenriksen@utah.gov

Schedule
Work days are Monday-Saturday 7 a.m. – 7 p.m.
Sunday work may occur as needed.
Work is expected to be completed by Summer of 2019
Schedules are subject to change due to weather conditions and material availability. 

Contact
To receive weekly e-mail updates on the project, or for questions or comments, please contact:
Hotline – (800)948.8286
E-mail – shenriksen@utah.gov
Website – udot.utah.gov/go/prbimproved

Autumn Crest Blvd ExtensionAutumnCrestExt

This project is intended to extend the Autumn Crest Blvd from the new high school to the Herriman City boundary (i.e. approximately 13800 South). Riverton City will construct the road from the Herriman City boundary to 13400 South. The design is complete and ready to advertise for bid, however, Right of Way (ROW) has not been acquired. Herriman City Will move forward with contractor procurement once ROW has been secured.

Desert Creek Trail

This project include a new trail along Rose Creek and provides a couple pedestrian crossings over the Creek. Once the project is complete, it will connect existing trail system at The Cove at Herriman Springs and extend the trail to the east end of Dester Creek development (i.e. 6600 West on the north side of the Creek). The project is in the design phase and we anticipate that it will be complete the beginning or spring of 2019.

Butterfield Park Trail/Maintenance Access Road Improvements

There is an existing gravel maintenance access and trail that runs along the east side of the Butterfield Park. This project will pave this access for future park events including the parade and car shows. This project is in the design phase and the construction phase will begin fall of 2018.

6000 West Roadway Widening

The scope of this project will include improvements along 6000 West such as new asphalt, curb and gutter, and sidewalk from Herriman Blvd. to approximately 80 feet short of Grandpere Ave. Once the design is complete and the anticipated funds are acquired, Herriman City will advertise for bids. We anticipate construction will begin this summer and complete before the end of the year.

Heritage Place Secondary Water Service Lateral Improvements 

Secondary water pipes and individual service laterals were installed when the Heritage Place development was constructed. Now that secondary water will be made available to each home, a meter box will be installed and ready for individual owners to connect at their discretion. This project will improve deficiencies of the existing service laterals and meter boxes for each home. The construction contract is currently underway and we anticipate completing the project the middle of this summer.

Herriman Blvd Landscaping and Street Light Improvements 

This project is planned to install landscape and street lights along the south side of Herriman Blvd from Herriman Main Street to 6400 West. This project is in the design phase and we anticipate advertising for bids before summer. Since the budget is not sufficient for the entire project, the contractor will install landscaping and street lights along the boulevard starting on the east end and working west as far as the allotted budget will allow. The remaining part of the project will be completed when additional funds are made available.

11800 South Mill & Overlay 

The roadway along 11800 South between 5600 West and Freedom Park Blvd is deteriorating. This project will mill off the top few inches of asphalt and overlay a new layer of asphalt in its place. This will be done to avoid a costly removal and replacement of all the asphalt if it’s allowed to age beyond disrepair. The project is intended to be complete in the middle of this fall.

Blackridge & Prairie Oaks Structures

The Blackridge Reservoir is in need of a storage facility for the maintenance of the reservoir and the park. Additionally, Herriman City plans to design and construct a new restroom facility for the Prairie Oaks park located at approximately 13900 South 7300 West. This project is intended to be design this spring and installed before the end of fall.

5600 West Herriman Main Street Intersection Pavement Improvements

The condition of the asphalt at this intersection is poor and will require a full replacement or a mill and overlay at the least. The scope of this project will extend beyond the intersection and along Herriman Main Street for a few hundred feet. Herriman City intends to complete the construction drawings this spring and complete installation before the end of this fall.

© Copyright 2013 Herriman City.